Hangzhou Fortune recently announced that the second phase of the Xinxingsheng Energy Co. Ltd project in Baotou City, Inner Mongolia, which includes a 500,000 Nm3/d LNG plant, has been successfully completed.
Hangzhou Fortune is responsible for the design of the process package, all of the plant’s process equipment, the design and manufacture of non-standard process equipment, as well as the procurement of control systems and electrical systems, project management, commissioning and training, and other technical support services.
The project lasted for one year, starting from the delivery of equipment in March 2014.
In October 2014, all the static equipment and machines were tested individually, and in April 2015 the whole plant was tested, with first product achieved on 25th April.